Main Contractor: Keltbray
Project Brief: Complete demolition of building
Situated off Sloane Square by the Underground Station, this 6 story end terrace building is to be completely demolished. The building has to be taken down very carefuly and efficiently as the site is only permitted 4 hours of ‘noisy work’ per day.
The site is very tight with roads on 3 of the 4 sides and a live building to the side which is remaining and must not be damaged. There is only 1 loading bay for trucks and the method of muck away had to be quick, quiet, efficient and produce minimal dust. TRUCKLOADER was the only option that could meet all the criteria and is now being unloaded into 20 or 40 yard skips for easy muckaway.
If you would like to know more about our efficient TRUCKLOADER system contact us now!
Leave A Comment